Saturday, 19th October 2019

Test of Main Power Failure, scheduled 1 month ago

We have been informed by our data center provider that they will perform a main power failure test. Both main power feeds of the data center are backed by independent UPS systems as well as diesel generators and all of our systems are connected to both power feeds. Therefore, we do not expect any impact.

Date / Time
Saturday, 2019-10-19, 13:00 CEST to 18:00 CEST

Expected Impact
No impact expected.

Thank you for your understanding.